Oct 2017 - Mar 2019
Demolition / New Build
12 & 2
The project was successfully completed in March 2019, with the ground floor now occupied by Superdrug and the first floor by an Anytime Fitness Gym. Despite the challenges, particularly with the steelwork, the project was delivered to a high standard, contributing to the local community, and enhancing the area’s architectural landscape.
1. Project Name: Balham High Road Development, London, SW12
2. Location:
3. Project Scope:
The project involved the complete demolition of an existing retail unit on Balham High Road, followed by the construction of a new four-story steel-framed building. The structure includes:
Ground Floor (Retail): 600 sqm, currently occupied by Superdrug.
First Floor (Leisure): 1,500 sqm, currently occupied by a Anytime Fitness Gym.
Second & Third Floors (Residential): 12 flats.
Construction Details:
Regulatory Compliance: